Transportation 

GREEN MOUNTAIN TRANSIT ROOF REPLACEMENT
Burlington, Vermont
2019

Photo of construction site.

PCI served as the Owner's Project Manager for Green Mountain Transit's roof replacement. This project spanned the course of several months, coming to completion in the fall of 2019. PCI monitored the project as construction progressed, inspecting for safety and proper installation, as well as performing Davis-Bacon interviews. The project was completed on time and under budget.

Burlington, Vermont, transit, transit center, ccta, gmt, downtown, busses, bus, future, new

DOWNTOWN TRANSIT STATION, GMT
Burlington, Vermont
2012-2016

The Downtown Burlington Station, over ten years in the planning, provides a central urban hub for Vermont’s largest public transportation authority. PCI assisted with site selection research and budget estimating during the planning process.  In the pre-construction phase we developed and administered a comprehensive contractor qualification process. We also conducted progress and compliance inspections on behalf of the owner throughout the construction phase.

TRANSIT PASSENGER SHELTERS
Addison, Chittenden, Franklin, Lamoille and Washington Counties, Vermont
2003-Present

Planning and management of site selection, permit acquisition, bid administration, contract administration, and project oversight.

Sitework, bus, busses, transit, public transportation, ccta, gmt, upgrade, Vermont

BUS BARN EXPANSION, CCTA
Burlington, Vermont
2009

Served as Owner’s Representative with services that included project planning, value management, contractor pre-qualification, bid administration, contract administration, progress inspections and general project oversight. Project was a $1.1M, 8,500 square foot addition to an existing bus storage facility serving Chittenden County Transportation Authority. Structural steel building addition, including extensive site and storm water work.

OFFICE FIT-UP, CCTA

Burlington, Vermont

2004-2005

​

PCI served as Owner’s Representative for VT’s largest non-profit transit authority with services that included project planning, bid administration, value management, contract administration, progress inspections and general project oversight. This project created 8,100 square feet of new office space in previously unfinished space. Construction hard costs came in under $46/ SF and the project had a total cost of $400K.

ccta, gmt, busses, bus, public transportation, transit, bus barn